Construction News - International Construction Industry
International
Construction News
UmweltBau GalaBau Bau Magazin

Fast-Tracking Partition Walls with Meva Formwork

MANILA/PHILIPPINES, May 22, 2013 - A new method using Meva’s wall formwork AluFix saves time and money. The crane-independent wall formwork system AluFix is extensively used for fast tracking because the panels can be carried manually and are ideally geared to the heights of partition walls.

 

Meva Formworks new method in Manila

Manila, Philippines: The Jazz Residences built by contractor Megawide consist of four residential towers up to 45 floors high. Shopping centers and parking levels on the ground connect the towers with each other. Every six working days another slab per tower is poured and so are the partition walls of a floor. They are poured in six cycles using a total of 110 m³ of concrete. 450 m² of wall formwork are used per cycle.

Modern homes are in increasing demand by the growing middle class in South East Asia and the Middle East. Building residential high-rises and housing blocks fast and efficiently without compromising quality or safety is a major challenge to local contractors in many Asian countries. The solution to the challenge is fast tracking the partition walls inside the buildings. Meva’s crane-independent wall formwork system AluFix is extensively used for fast tracking because the panels can be carried manually and are ideally geared to the heights of partition walls.
Fast-tracking partition walls eases the building process.
How does fast-tracking work? First, the structural walls of a floor are erected, but no partition walls. Then, large panel areas of slab formwork are set up. This is done much faster than usually because there is no hindering inside walls. After pouring the slab and stripping the slab formwork, the partition walls on that floor are poured.

Sizes to fit any wall size

With four panels heights from 132 to 300 cm and over 10 widths from 20 to 75 cm per height, AluFix easily handles typical room heights and partition walls of any size and form. If the walls differ in height and width from standard sizes or from each other, the panels can be combined vertically and horizontally to reduce the panel selection to be held on stock on site. Standard fillers are available to bridge gaps. As the formwork for the partition walls extends to or almost to the poured slab, the concrete is poured through holes in the slab. If this is not possible, e.g. under RC beams, panels with filling nozzles are used for concrete pouring.

An efficient method with better concrete surface

Subsequent partition walls can also be erected using hollow bricks, Spraycrete or Macro panels (prefabricated concrete hollow panels). Yet by using AluFix, contractors save efforts, time and costs for different reasons: no material (hollow bricks or Macro panels) needs to be transported, the concrete finish achieved with AluFix is much better than with hollow bricks and plastering work is minimised. bi

A typical partition wall inside Jazz Residences that is poured using AluFix wall formwork. The 2.40 m high walls resting on beams are poured with horizontal panels that have filling nozzles. The 2.90 m high walls are poured using vertical panels and the concrete is poured through holes in the slab. | pictures: Meva